.....

RE Library Home

Search Library

Add This Library
To Your Web Site

Real Estate Forum

Advertise With Us

Submit Your Articles
To This Library

Library Site Map

MADE Homes - Affordable, Entry-Level Homes - Builder's Journal - 11/22/2004 - Real Estate Home House Condo

MADE Homes - Marketable, Affordable, Durable, Entry-Level Homes - Builder's Journal

Builder's Journal

Week 18: Trades Finish Work (Part II)
Week 17: Trades Finish Work (Part I)
Week 16: Hard Floors Installation
Week 15: Exterior Painting
Week 14: Exterior Decking
Week 13: Siding Installation
Week 12: Drywall, Trim, and Paint
Week 11: Roofing
Week 10: Insulation Installation
Week 9: Rough-Ins II: Electrical and 
Budget-Wise Structured Wiring and Security

Week 8: Rough-Ins: HVAC, Fire Protection, Plumbing
Week 7: Installation of Weather Barrier, Flashing,
 Windows, Doors

Week 6: Installation of the Garage Stemwalls
Week 5: Framing the Walls and Roof
Week 4: Let's Get Framing!
Week 3: Pouring the Slab
Week 2: Setting the Basement Walls
Week 1: Construction Begins!!



Week 18: A good place to invest in energy savings is the lighting package in a home. Most lighting manufacturers now offer fairly good selections of residential fluorescent fixtures for both interior and exterior applications. Cabinets in affordable homes are typically very plain, but for little additional cost, they can be made to look custom.

Back to top

Trades Finish Work (Part II)
Trades Finish Work (Part II)

Trades Finish Work
Trades Finish Work (Part I)

Week 17: HVAC installation, plumbing, and electrical work are highlighted this week.

Back to top


Week 16: We wanted to see what minor changes we could make in either material selection or installation procedures to significantly increase the durability of the hard surface flooring without adding substantial costs.

Back to top

Hard Floors Installation
Hard Floors Installation

Exterior Painting
Exterior Painting

Week 15: Painting is a very important part of a fiber-cement siding system. It can either make or break the overall appearance and performance of the job.

Back to top


Week 14: We selected a tongue-and-groove, wood/plastic composite decking material for the first two MADE houses. This material costs about 60 to 70 percent more than radius edge 5/4" x 6" CCA pressure-treated decking. Despite its higher cost, we chose the composite decking because it requires no sealing and has few exposed fasteners.

Back to top

Exterior Decking
Exterior Decking

Siding Installation
Siding Installation

Week 13: We chose to use fiber-cement siding for the first two MADE houses for both the look and warranty. However, we wanted to see if there was a way to enhance its durability. We looked at the three major components of a fiber-cement siding system: siding/trim; caulk; and paint. The caulking was identified as the weakest link. Typically, the caulk fails, causing the paint to fail, then the siding. So we set out to develop a system that does not need caulk.

Back to top


Week 12: Nothing special or fancy for this part of the MADE construction - just good, solid details

Back to top

Drywall, Trim, and Paint
Drywall, Trim, and Paint

Insulation Installation
Roofing

Week 11: Two of the four MADE Homes will have metal roofs. However, on the first two, we installed a 40-year fiberglass shingle. Special attention was given to details to increase the durability of the roof assembly.

Back to top


Week 10: Insulation choices are similar to the HVAC equipment choices in the sense that a balance must be reached between efficiency gains and initial costs. As with the HVAC equipment, the insulation choices for the MADE homes conform to an Energy Star Builder Option Package.

Back to top

Insulation Installation
Insulation Installation

Electrical and Budget-Wise Structured Wiring and Security
Electrical and Budget-Wise Structured Wiring and Security

Week 9: With computers now an integral part of everyday life, and security a vital concern for homeowners, we would be remiss not to include a structured wiring and security package in the MADE Homes. Nothing too new or innovative was used for the electrical rough-ins.

Back to top


Week 8: The HVAC systems for the MADE Homes were designed to maximize the amount of ductwork located within conditioned space. Fire sprinkler systems are required, which adds substantial costs and requires separate permits and approvals. Incorporating stacked bathrooms in the design of the home saves labor and material by reducing the amount of piping and drilling. Reduced piping also means less potential for leaks!

Back to top

Rough-Ins: HVAC, Electrical, Fire Protection, Plumbing
Rough-Ins: HVAC, Electrical, Fire Protection, Plumbing

Installation of Weather Barrier, Flashing, Windows, Doors
Installation of Weather Barrier, Flashing, Windows, Doors

Week 7: In terms of a home's durability, the exterior cladding is perhaps the most important factor. As with many facets of construction, what the consumer can't see in the final product are often the most critical elements.

Back to top


Week 6: After backfilling was complete and the framers were working on the second story walls, there was time to get the precast stemwalls for the garages installed. Then the garages, porch roofs, and returns were framed.

Back to top

Installation of the Garage Stemwalls

Framing the Walls and Roof
Framing the Walls and Roof

Week 5: Traditional stick-framed wood construction was chosen for the walls of the MADE Homes. This choice is so traditional, it's actually innovative! Stick framing the roofs allows for maximum area on the second story, both for living area and storage.

Back to top


Week 4: With poured concrete walls, after pouring the slab, the next step is usually backfilling. With precast foundation walls, however, the first floor framing must be completed prior to backfilling as it provides essential bracing. With dry weather forecasted, we opted to first frame the first floors for both units so that backfilling could take place as quickly as possible.

Back to top

Let's Get Framing!

Pouring the slab
Pouring the Slab

Week 3: After the precast foundation walls were set and a chemical termite treatment was completed, preparing the slab could not have been easier. The gravel was already in place and within an inch of grade. A crew of four completed the installation of the poly vapor barrier, wire mesh, and thickened areas for both units in about five hours.

Back to top


Week 2: Installation of the Superior Walls for Lot 64 took place on Monday; Lot 63 was done on Tuesday. The installation crew was comprised of five workers, including the crane operator. Each installation took about three hours total. Although, the basement will not be finished initially, a bathroom rough-in will provide future owners with a cost-effective bathroom addition.

Back to top

Setting Superior Walls

Picture of construction
Construction Begins!!

Week 1: Construction on the MADE Demonstration Homes finally began Monday with the excavation of the basement for the Aspen unit on Lot 64 of the National Research Home Park. Lot 63 was excavated Tuesday.

Back to top


Related Articles:
Ask Realty Times - April 14, 2006 | Where Can You Browse For Affordable Housing?
The Last Great Real Estate Secret - Part 4y | Headlines At a Glance - July 3, 2006
 

Article reprinted with permission Copyright ©. Article presentation format, categories, and content management system Copyright © Nemmar.com.

.....


Copyright © 1990-2007 All Rights Reserved - Terms and Conditions Our copyright is very strictly enforced!
Page copy protected against web site content infringement by Copyscape